Flooding and Run-Off Remediation Projects

In Engineering Design Phase

Great Falls Court

Construction of a drainage swale approximately 220 feet in length, and two terraced short retaining walls. The project has been awarded to a contractor and construction will begin Spring of 2023. 

920 Brookvale Terrace 

Installation of 150 feet of new sewer pipe, 3 new inlets, & 2 new manholes. MSD to take over maintenance of new infrastructure. Construction will be bid out Spring/Summer 2023.

Timberleigh Brookvale Terrace

Installation of 275 feet of new sewer pipe, 4 new inlets, & 2 manholes. MSD to take over maintenance of new infrastructure. Construction Bid out Spring/Summer 2023. 

Glan Tai Stormwater

Installation of 1 double inlet & 2 trench drains the width of the road. MSD to take over maintenance of new stormwater inlets. Construction Bid out Summer/Fall 2023.

Grenadier Lane

Installation of 5 new curb inlets, 3 new trench drains, and grading work. MSD to take over maintenance of new stormwater inlets. Construction Bid out Summer/Fall 2023.

Recently Completed

Marie/Baxter Project

 500 linear feet of new storm sewer in yards & street, 4 inlets, 2 manholes, & grading. MSD to take over maintenance of new infrastructure.   This project was completed in Summer of 2022.

Trench Drain Replacements  

Replaced three (3) existing 26 foot long roadway trench drains that were in structural disrepair at 5 San Souci Drive, 932 Delmonico Drive, and 1446 Sunnytree Lane. This project was completed in Fall of 2022.