In Engineering Design Phase
Great Falls Court
Construction of a drainage swale approximately 220 feet in length, and two terraced short retaining walls. The project has been awarded to a contractor and construction will begin Spring of 2023.
920 Brookvale Terrace
Installation of 150 feet of new sewer pipe, 3 new inlets, & 2 new manholes. MSD to take over maintenance of new infrastructure. Construction will be bid out Spring/Summer 2023.
Timberleigh Brookvale Terrace
Installation of 275 feet of new sewer pipe, 4 new inlets, & 2 manholes. MSD to take over maintenance of new infrastructure. Construction Bid out Spring/Summer 2023.
Glan Tai Stormwater
Installation of 1 double inlet & 2 trench drains the width of the road. MSD to take over maintenance of new stormwater inlets. Construction Bid out Summer/Fall 2023.
Grenadier Lane
Installation of 5 new curb inlets, 3 new trench drains, and grading work. MSD to take over maintenance of new stormwater inlets. Construction Bid out Summer/Fall 2023.
Recently Completed
Marie/Baxter Project
500 linear feet of new storm sewer in yards & street, 4 inlets, 2 manholes, & grading. MSD to take over maintenance of new infrastructure. This project was completed in Summer of 2022.
Trench Drain Replacements
Replaced three (3) existing 26 foot long roadway trench drains that were in structural disrepair at 5 San Souci Drive, 932 Delmonico Drive, and 1446 Sunnytree Lane. This project was completed in Fall of 2022.